Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 11/10: Pavement markings and remaining restoration items to be completed.
Weston Ave (CR-X to Ryan St):
- Week of 11/10: The shoulder will be placed, work on the storm pond at Lindenwood Ct will take place and potentially pavement markings later in the week along with remaining restoration work.
- Week of 11/17: Restoration, pavement markings and other outstanding items.
Fuller St:
- Week of 11/10: Paving of remaining asphalt driveways to be completed around mid-week as temperatures get warmer. Complete restoration, sign installations, mailboxes and other outstanding items.
- Week of 11/17: Complete any remaining work before winter.
Hospital Area Paving:
- Week of 11/10: Paving of Weston Ave from CR-X to Birch St.
- Week of 11/17: Finish Weston Ave if not done, potentially start working on Birch St.
Weekly updates on roadway projects are released every Friday on Facebook.