Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 9/8: Continue working on street grading, traffic signals and concrete work along the eastbound lanes.
-Week of 9/15: Continue with concrete work, road grading if needed, traffic signals and potentially restoration.
Weston Ave (CR-X to Ryan St):
- Week of 9/8: Water and sewer service lateral installation will continue from Heeren going east. Grading crew will be working from roughly the ATC powerline heading then west towards Heeren. Rock blasting east of Lindenwood Ct is expected to start Monday.
- Week of 9/15: Sewer and water installation will then continue once blasting is complete between Lindenwood Ct and Ryan St. Grading crew will continue building the road between the ATC powerline and Heeren St.
Fuller St:
- Week of 9/8: North of Thomas Ave the crew will be working on restoration of grass areas. Then between Schofield Ave and Moyer, storm sewer installation and watermain installation will continue near the Waste Management area north towards Moyer. The grading crew will be working on getting the road built once the utility crew completes the underground work.
- Week of 9/15: Work should primarily be then on the southern portion as pipework between Waste Management and Moyer gets completed.
Business Park Paving (Commerce Dr and Ryan St):
- Week of 9/8: Paving of Commerce Dr from Ryan St to Rickyval St is planned along with structure adjustments on Ryan St.
- Week of 9/15: Pulverizing of Ryan St and work on getting the road graded out.
Asphalt Overlay Projects:
Asphalt overlays are planned for the below streets. Crews have or will be completing prep work ahead of the overlay paving which includes adjusting all manholes and water valves within the pavement as well as milling along the curb lines or driveways. Paving of these areas is anticipated to be the week of 9/15.
- Post Ave (West of BUS 51)
- Cortez, Coronado and Lawndale (North of Jelinek)
- Terrier and Birchwood Ln (South of Jelinek)
- Prairie St and Westfair St (West of Mesker)
- Alex St (West of Sandy Ln)
- Michael Dr
- Cheryl Dr
- Jacob St
- Twin Pines Ln
- Morning View (East of Twin Pines)
- Babl Ln (East of Twin Pines)
- Saxon Ave
- Regent St
- Meridian St
- Jean Ellen St
- Sternberg Ave (Scott St to Mesker St)
Shorey Ave Repaving (County Road X to Anastasia Dr): Paving of Shorey is expected to take place on Tuesday 9/9 and Wednesday 9/10.
Weekly updates on roadway projects are released every Friday on Facebook.