Village of Weston Building
view the original message here
Village Meetings

Upcoming Meetings: 
July 31st - Aug 1st

  • Informational Session to Learn More About the Fire Fee, Aug 6th, 6:00 p.m. - 7:30 p.m.
Line

Poll Question:

What articles do you value the most in the quarterly 
Weston Wire Newsletter?

line
Weekly Spotlight
Fire Fee

What is a Fire Fee? 
Join us on August 6th to learn more, a virtual option is available to attend and the meeting will be recorded.

lottery
Auto Pay
Closure

***UPDATE*** Integrity Grading and Excavating (Prime Contractor on Weston Avenue Reconstruction project) is falling behind on their schedule and will be delaying the intersection closure at Weston Avenue and Ryan Street to the week of August 4th.

We ask that our residents and local travelers be prepared and plan their alternative route for that week and continue to be patient during this temporary closure. Above is a map of some possible alternative routes to travel to your destination while the intersection closure is in place.


drug box

Help keep our community safe and healthy by dropping off your unwanted or unused medications at the Mountain Bay Metro Police Department, 211 Grand Avenue, Rothschild.

Music

If you haven't been to a concert yet, you're missing out! 
Weston Acoustic Concert Series for August is Howard Gripp with Palmetto Grill Food Truck serving food while you enjoy the concert. Come out for a night of music and great food!

Concert Off the Square
Join Wausau Events for our "Concert OFF the Square" in 2025!
This concert will NOT be held at the 400 Block, but instead held at Kennedy Park in Weston! Food vendors available, with live music by HYDE.
The event is FREE to attend.
Public Works Report

Updates for current roadway projects:

Schofield Ave (Normandy St to Birch St):
- Week of 7/28
: Alderson St south of Schofield Ave will be closed for sanitary sewer and watermain work.  By the end of the week the intersection should be back open on temporary pavement.  For the rest of the corridor, removal of concrete pavement will continue.  

- Week of 8/4: Continue work on utility replacement.  

Weston Ave (CR-X to Ryan St):
- Week of 7/28
: Sanitary sewer work east of Heeren St towards Ryan St will continue. The base between Von Kanel and Heeren will be regraded and prepped for paving along with work in the ditches.

- Week of 8/4: Utility work on the north side of Weston Ave across Ryan St will begin.  This will close Ryan St north of Weston Ave. Paving of Weston Ave between Von Kanel and Heeren St is anticipated to be done this week.

  • Note: Ryan St will be closed north of Weston Ave the week of 8/4 to get the sanitary sewer, watermain and storm sewer installed across Ryan St.  

 Fuller St:
- Week of 7/28: Continue to install new storm sewer along Fuller heading north from Rogan Ln. Road building has begun and will continue north of Rogan Ln towards Ross Ave as well.

- Week of 8/4:  It is anticipated the pipe crew will be moving to the Schofield Ave intersection with Fuller and begin working on new pipe installations there heading then north towards Rogan Ln while the grading crew will continue building new roadway north towards Ross from Thomas Ave.

Shorey Ave Repaving (County Road X to Anastasia Dr): This project is still on hold until work on Weston Ave can be completed through the Heeren intersection.

Weekly updates on roadway projects are released every Friday on Facebook.

Flushing
Cats

We Want Your Feedback! 

Please submit your ideas for our newsletters!

jgebert@westonwi.gov

Line

FOLLOW, LIKE, AND SUBSCRIBE TO OUR SOCIALS! 

Click an icon below to view more

Line
Subscribe to notifications
NEXTDOOR CLICKABLE LINK
Listen to Meetings on Youtube
Farmers Market FB Page
Main FB Page
Weston Aquatic Center FB Page
Share on Facebook
Share on Twitter
Share via Email

Copyright 2023 Weston WI. All Rights Reserved.
4747 Camp Phillips Rd, Weston WI 54476

Powered by
CivicSend - A product of CivicPlus