Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 7/21: Removal of concrete pavement will continue. Sanitary sewer manhole replacement will start between Normandy St and Alderson St.
- Week of 7/28: Continue work on sanitary sewer manhole replacements.
Weston Ave (CR-X to Ryan St):
- Week of 7/21: Road building from Von Kanel to Heeren St to continue along with sanitary sewer installation resuming east of Heeren St. There is roughly 250 feet of road left to build to get through the Heeren intersection.
- Week of 7/28: Sanitary sewer work to start at the Ryan St and Weston Ave intersection. Paving between Von Kanel and Heeren expected the later part of this week.
- Note: Ryan St will be closed north of Weston Ave the week of 7/28 to get the sanitary sewer, watermain and storm sewer installed across Ryan St.
Fuller St:
- Week of 7/21: Continue to install new storm sewer along Fuller heading north from Rogan Ln along with the below planned water valve and hydrant work
- Tuesday 7/22: Watermain connection at Fuller St and Ross Ave
- With this connection there will be a traffic lane shift to the north which will stay in place for several weeks.
- The crew will continue excavating out the pond at Kellyland Park as well
- Week of 7/28: Continue with storm sewer installation heading north to Ross Ave along with continued excavation of the pond at Kellyland Park.
Shorey Ave Repaving (County Road X to Anastasia Dr): This project is still on hold until work on Weston Ave can be completed through the Heeren intersection.
Weekly updates on roadway projects are released every Friday on Facebook.