Village of Weston Building
view the original message here
Village Meetings

Upcoming Meetings: 
July 10th - July 17th

  • Public Works & Utility, July 14th, 4:30 p.m.
  • Plan Commission, July 14th, 6:00 p.m.
Line

Poll Question:

We want your input! If you already provided your thought(s) through the link below, thank you - if not, please let us know what you would like included in the upcoming Comprehensive Plan Survey.

 
The Village is currently in the process of updating our Comprehensive Plan, which is our ten-year, broad-based strategy document to guide future development of the community. 

As part of the plan update a Community Survey will be development and distributed Village wide. We would welcome resident input on questions they would like to see included in the survey! Is there something you would like asked of the entire community? Share your thoughts on survey questions HERE.

line
Weekly Spotlight

Join us for the
Weston Acoustic Concert Series


In case you didn’t hear, Weston resident, and musician, Jackson Taylor has organized the first ever “Weston Acoustic Concert Series.”  This consists of various singers who are performing at Machmueller Park, 7200 Quentin Street, each Tuesday, during July and August, from 7pm – 8:30pm. 

Jackson’s vision and purpose of these events is to bring live music to the community, in a family-friendly setting.

The concerts are free to attend, and carry-ins are welcome. People just need to bring a chair and enjoy! Each event will have a food truck available for anyone who wants to purchase food.

If rain/bad weather is occurring, the event will get moved over to Hutch’s Kelly Club, 4810 Ross Avenue. To see the full schedule, click on the poster below. 

music
Agenda

The Public Works & Utility Committee meeting will be held on Monday, July 14, 2025, at 4:30 p.m. in the Village Board Room. Click here to see the entire agenda & packet.

Agenda

The Plan Commission meeting will be held on Monday, July 14, 2025, at 6:00 p.m. in the Village Board Room. Click here to see the entire agenda & packet.

Taxes

Second installment payments should be mailed to the MARATHON COUNTY TREASURER, 500 Forest Street, Wausau, WI 54403

Flushing

Click HERE to see where flushing currently is and where they will be going next so you can stay up to date.

Stickers
Job
Taste and Glow

Funded in part by the Weston Tourism Commission

Public Works Report

Updates for current roadway projects:

Schofield Ave (Normandy St to Birch St):
- Week of 7/7
: Final layer of asphalt paving is expected to be completed early in the week with traffic then being shifted to the new lanes by Friday 7/11.

- Week of 7/14: Work begins on the southern lanes with the concrete pavement removal.

Weston Ave (CR-X to Ryan St):
- Week of 7/7
: Road building from Von Kanel to Heeren St to continue.  

- Week of 7/14: Road building through the Heeren intersection to continue if not finished and then work on sanitary sewer to start up again.

Fuller St:

- Week of 7/7: Continue to install new storm sewer along Fuller heading north from Rogan Ln.  

    • Water valve and hydrant work is expected to be completed at Thomas and Fuller. on Monday
    • Tricia and Fuller on Tuesday
    • High Ridge and Fuller on Wednesday
    • Morning View and Fuller on Friday
  • The crew will continue excavating out the pond at Kellyland Park as well

- Week of 7/14: Continue with storm sewer and water valve/hydrant work heading north to Ross Ave along with continued excavation of the pond at Kellyland Park.

Asphalt Sealing:
- Week of 7/7: Fahrner was rained out for parts of this past week so they’ll be continuing to work through the residential streets this coming week.

Crack Sealing:
- Week of 7/7: Precision Sealcoating will continue crack sealing throughout the Village on various asphalt streets.

Weekly updates on roadway projects are released every Friday on Facebook.

Dog Park
directions

Heading to the Weston dog park? You may want to take an alternate route with the construction Fuller Street. The best route to take at this time is Ross Avenue to Kellyland Street to Moyer Avenue. Then Fuller Street to Rogan Lane. Thank you for your patience as we make improvements to our roads in the Village of Weston!

We Want Your Feedback! 

Please submit your ideas for our newsletters!

jgebert@westonwi.gov

Line

FOLLOW, LIKE, AND SUBSCRIBE TO OUR SOCIALS! 

Click an icon below to view more

Line
Subscribe to notifications
NEXTDOOR CLICKABLE LINK
Listen to Meetings on Youtube
Farmers Market FB Page
Main FB Page
Weston Aquatic Center FB Page
Share on Facebook
Share on Twitter
Share via Email

Copyright 2023 Weston WI. All Rights Reserved.
4747 Camp Phillips Rd, Weston WI 54476

Powered by
CivicSend - A product of CivicPlus