Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 6/30: Restoration of the north boulevard continues along with utility adjustments. Final layer of asphalt paving could possibly occur later in the week as well, weather permitting.
- Week of 7/7: Finish any remaining restoration and utility adjustments and then finalize paving on the westbound lanes. The schedule right now is to switch traffic to the new asphalt lanes the week of 7/14 and then begin working on the southern lanes.
Weston Ave (CR-X to Ryan St):
- Week of 6/30: Road building from Von Kanel to Heeren St to continue. With the wet weather this past week not a lot of work was able to be accomplished with the roadway.
- Week of 7/7: Road building through the Heeren intersection to continue if not finished and then work on sanitary sewer to start up again.
Fuller St:
- Week of 6/30: Continue to install new storm sewer along Fuller heading north from Rogan Ln. Potential for some hydrant and valve work later in the week.
- Week of 7/7: Continue with storm sewer working north towards Ross Ave along with spot hydrant and water valve work.
Asphalt Sealing:
- Week of 6/30: Fahrner is finishing up Schofield Ave (Ryan St to CR-J) as of 6/27. They’ll be working through the subdivisions of Windemere Oaks and Crestwood Acres along with Neupert Ave the week of 6/30.
Crack Sealing:
- Week of 6/30: Precision Sealcoating will continue crack sealing throughout the Village on various asphalt streets.