Schofield Ave (Normandy St to Birch St):
- Week of 6/16: As weather permits, work on Alderson Street north of Schofield Avenue will be completed. Road building and paving of the first layer of asphalt on the westbound lanes is scheduled to occur with restoration of the north boulevard likely to start towards the end of the week.
- Week of 6/23: Finish restoration work, utility adjustments and possibly surface paving.
Weston Ave (CR-X to Ryan St):
- Week of 6/16: Water and sewer lateral installation will continue between Von Kanel and Heeren Street. Blasting of rock for the sanitary sewer installation is likely to occur east of Heeren with then a continuation of sanitary sewer installation heading east of Heeren.
- Week of 6/23: Sanitary sewer will continue along with road building between Von Kanel and Heeren Street.
Fuller St:
Project is expected to start the week of 6/16 starting with the pond work at Kellyland Park.