Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 6/9: Alderson St north of Schofield Ave towards the Associated Bank entrance will be closed for the week for new watermain installation. Fox St will be opened up so traffic can utilize a detour of Weiland to Fox in lieu of Alderson St. Work will continue on building the road between Normandy and Birch.
- Week of 6/16: Alderson St north of Schofield Ave work will be completed (new curb and pavement). Road building and then paving of the westbound lanes is expected to occur later in the week and likely continue into the following week.
Weston Ave (CR-X to Ryan St):
- Week of 6/9: Water and sewer lateral installation will continue between Von Kanel and Heeren St. Blasting of rock for the sanitary sewer installation is likely to occur east of Heeren with then a continuation of sanitary sewer installation heading east of Heeren.
- Week of 6/16: Sanitary sewer will continue along with road building between Von Kanel and Heeren St.
Fuller St:
Project is expected to start the week or 6/16.
Weekly updates on roadway projects are released every Friday on Facebook.