Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 5/26: The contractor will continue with pouring curb and gutter within the westbound lanes. The goal is to have all curb and gutter completed between Normandy and Birch by the end of the week. They will also be working on pouring new sidewalk and driveway aprons later in the week. New traffic signal bases will be getting poured in place as well.
- Week of 6/2: Concrete sidewalk and driveway aprons will continue with gravel roadway building taking place as well.
Weston Ave (CR-X to Ryan St):
- Week of 5/26: Sanitary sewer work to continue east of Heeren St. along with watermain work from Von Kanel towards Heeren St.
- Week of 6/2: Sanitary sewer installation to continue with watermain installation heading east.
E Jelinek Ave and Von Kanel:
- Week of 5/26: Restoration of ditches and asphalt repairs are scheduled to finish up this coming week. This past week the crews were rained out a few days and were not quite able to get all the way to Camp Phillips Rd/CR-X.
Fuller St:
Project is expected to start in early June. Special Assessment Hearing is scheduled for Thursday, May 29th at 6pm.
Weekly updates on roadway projects are released every Friday on Facebook.