 Michael Wodalski, Director of Public Works
|
2025 Public Works Projects The Village of Weston has a Capital Improvement Plan which includes facilities, streets and utility projects as well as major equipment purchases. The 2025 projects include the following:
Street Projects: - Schofield Ave and Mesker St Intersection will be having traffic signals, which should be installed by April 2025. As part of the Schofield Ave corridor study this intersection was analyzed for improvements and adding signals here will improve turning and crossing Schofield Avenue at Mesker Street.
- Schofield Ave (Normandy St to Birch St): The Village has received a $2,652,390 grant to reconstruct Schofield Ave along this corridor. The project includes new pavement and updates to the signalized intersections at Alderson Street, Target/ACE/Pick N’Save as well as Birch Street.
- Fuller St is planned to be reconstructed from Schofield Avenue to Ross Avenue. The reconstruction will rebuild the road as well as add pedestrian accommodations along the entire route. Along with this project, a storm water basin will be constructed within the Kellyland Park greenspace which will then double as a stormwater infiltration basin during rain events and then a grass field for recreation use when it’s not raining.
- Weston Ave Reconstruction (Von Kanel to Ryan St) this 1.25 mile stretch is planned to be reconstructed in 2025. The project includes complete street reconstruction, looping of watermain and installation of sanitary sewer.
- Shorey Ave Repaving (CR-X to Heeren St) will be repaved and coordinated with the Weston Avenue project.
- Business Park (Commerce Dr (west of RickyVal) and Ryan St (Commerce to Schofield Ave) will be repaved this summer to complete the Business Park repaving project that was started in 2024.
Utility Projects: - PFAS Treatment: The Village has received a Safe Drinking Water Loan from the Wisconsin Department of Natural Resources with $3.1 Million of it having principal forgiveness to construct a PFAS removal plant for Well 4. Well 3 improvements are being planned for 2026 construction.
|
|
|
|
 TONIGHT IS Pizza for a Cause. Join us and dine out; 10% of sales will be donated to the Kennedy Park Renovation Project. The Kennedy Park Project is a collaboration between the Village of Weston Parks & Recreation Committee/Department, the Community Foundation of North Central Wisconsin, D.C. Everest Youth Baseball, JV Baseball, Everest Fastpitch, JV Softball, and Everest Youth Hockey. The plans include five baseball/softball fields, hockey rink for outdoor skating, walking paths, concession stand, updated shade areas, playground equipment and green space.
|
|
|
|
 Just a quick update! The Weston Weekly E-newsletter will no longer be coming out on Tuesdays. As of 1/23/2025, it will be coming out every Thursday going forward.
|
|
|
|
We Want Your Feedback! Please submit your ideas for our newsletters!
|
|
|
|
FOLLOW, LIKE, AND SUBSCRIBE TO OUR SOCIALS! Click an icon below to view more
|
|
|
|