[ARCHIVED] Road Construction Update

PW Report

Schofield Ave (Normandy St to Birch St)

  • Week of 10/6: Continue working on street grading, traffic signals and concrete work along the eastbound lanes.  Potentially starting to pave asphalt late in the week. 
  • Week of 10/13: Continue with concrete work and asphalt paving of eastbound lanes. 

Weston Ave (CR-X to Ryan St)

  • Week of 10/6: Ryan St at Weston Ave will be closed to through traffic (north/south) starting Tuesday 10/7 thru Friday 10/10 and then opened up by the weekend to get the intersection built.  Traffic will still be able to move east/west through the intersection.  Watermain and sanitary sewer installation will continue west of Ryan St towards Lindenwood Ct. 
  • Week of 10/13: Concrete work from the ATC Powerlines heading east is anticipated to be poured.  Roadway grading will follow concrete work with paving anticipated the following week (10/20).  Water and sewer installation will continue between Ryan St and Lindenwood Ct.

 Fuller St

  • Week of 10/6: North of Thomas Ave asphalt paving is planned early in the week.  Then between Schofield Ave and Meridian, paving of the multi-use path on the east side of the road and then restoration behind the curb.  From Meridian north, pipe work will be finished up and the road will be built through that stretch.  Storm sewer installation along Rogan Ln from the park to Fuller St is planned to begin. 
  • Week of 10/13: Concrete curb between Thomas and Meridian to be poured, storm sewer installation on Rogan Ln to continue and restoration on the south side to continue.  Fuller St just north of Schofield Ave will likely be closed for several days this week for new concrete pavement to be poured. 

Hospital Area Paving

  • Week of 10/6: Cranberry Blvd is planned for continued road building and paving.  Concrete curb work on Ministry Pkwy is continuing. 
  • Week of 10/13: Finish work on Cranberry Blvd, begin roadwork on Ministry.  

Asphalt Overlay Projects:

  • Paving of the below areas are planned to be worked on 10/6 to 10/8.
    • Post Ave (West of BUS 51)
    • Cortez, Coronado and Lawndale (North of Jelinek)
    • Terrier and Birchwood Ln (South of Jelinek)
    • Alex St (West of Sandy Ln)
    • Michael Dr
    • Cheryl Dr
    • Jacob St
    • Twin Pines Ln
    • Morning View (East of Twin Pines)
    • Babl Ln (East of Twin Pines)
    • Saxon Ave
    • Regent St
    • Meridian St

Additional Info...
Facebook Twitter Email

Other News in Home - News & Announcements

Free Rabies Clinic

Posted on: March 3, 2026

The Wire - March Issue

Posted on: March 4, 2026

2026 Budget

Posted on: September 10, 2025

Notify Me

Posted on: February 22, 2024 | Last Modified on: May 19, 2025