Schofield Ave (Normandy St to Birch St):
- Week of 8/11: Storm sewer work will continue next week along with some road grading.
- Week of 8/18: Storm sewer, sanitary lining and road building will continue, concrete work is anticipated to start the week of 8/25.
Weston Ave (CR-X to Ryan St):
- Week of 8/11: Ryan St is opened back up with a temporary gravel patch. Sanitary sewer and watermain work east of Heeren St towards Ryan St will continue. Weston Ave between Von Kanel and Heeren is scheduled for being paved on Tuesday 8/12.
- Week of 8/18: Sanitary sewer and watermain work will continue.
Fuller St:
- Week of 8/11: If needed, grading between Rogan and Ross will be completed. The grading crew will then go back to working on the storm pond off Rogan or begin working on Schofield Ave heading north if the pipe crew is far enough ahead. Pipe crew will continue working on storm sewer from Schofield Ave heading north towards Rogan. Temporary water services will be setup south of Rogan as well.
- Week of 8/18: Grading from Schofield Ave north towards Rogan is expected to be ongoing along with watermain work south of Rogan.
Shorey Ave Repaving (County Road X to Anastasia Dr):
- This project is still on hold until work on Weston Ave can be completed through the Heeren intersection