- Home
- Departments
- Public Works & Utilities
- Public Works Projects
Public Works Projects
The Village of Weston renews its Capital Improvement Plan (CIP) on a 5-year cycle to plan and budget public infrastructure projects across the entire community. The Village's CIP is a working document used for discussion purposes during meetings between staff and board and committee members, residents and business owners, construction and utility representatives, and for annual budgeting purposes.
A lot of effort and consideration goes into preparing the CIP to make sure all priorities are addressed while remaining mindful of the community and its tax payers. Below is a pdf document that helps describe the consideration and effort that is required to prepare the CIP.
Future Project Planning
Below are the capital improvement projects planned for the identified years. If you have any questions regarding previous projects within the Village of Weston, please feel free to reach out to our Public Works & Utilities staff listed here.
Are you a Consultant, Contractor, or Supplier, looking for an opportunity to work with
the Village of Weston on one of its upcoming infrastructure projects?
If so, please consider visiting the Village's bidding website using the provided Public Bidding link.
2026 Public Works Planning Projects
Projects for 2025 include:
Village of Weston Bicycle and Pedestrian Master Plan, 6999-17-01
- Planning Consultant: HKGi
- Tentative Schedule: Summer 2025 - Summer 2026
- Project Summary: The Village of Weston received a Transportation Alternatives Project (TAP) grant for a Bicycle and Pedestrian Masterplan from the State of Wisconsin which will be incorporated inro the Village’s Comprehensive Plan. The planning study will focus on identifying key gaps in the Village’s bicycle and pedestrian network and looking at projects to close those gaps.
2026 Street and Utility Capital Improvement Projects
Projects for 2026 include:
Bloedel Avenue (Pine Park St-Alderson St) and Well No. 1 (Kennedy Park-Bloedel Ave)
↪Construction Updates (Coming Soon)
- Prime Contractor: TBD
- Tentative Construction Schedule: May 2026 - October 2026
- Project Summary: Removal of existing road pavement and base, installation of drinking water main, water valves, water services, sanitary sewer, manholes, sewer services, storm sewer, infiltration swales, regrading the road, installation and compaction of road base, asphalt pavement, concrete shoulder, concrete sidewalk (north side and possibly between Neupart Ave and Bloedel Ave), pavement marking, permanent signing, and restoration of the areas outside the roadway.
Bayberry Street (Ross Ave-Concord Ave) and Concord Avenue (Bayberry St-Camp Phillips Rd/CTH X)
↪Construction Updates (Coming Soon)
- Prime Contractor: TBD
- Tentative Construction Schedule: June 2026 - October 2026
- Project Summary: Removal of existing road pavement and base, installation of storm sewer, infiltration swales, water and sewer adjustments and rehabilitations, regrading the road, road widening, installation and compaction of road base, asphalt pavement, concrete shoulder, concrete sidewalk (west/north side), pavement marking, permanent signing, and restoration of the areas outside the roadway.
Jelinek Avenue and Alderson Street Intersection (Roundabout)
↪Construction Updates (Coming Soon)
- Prime Contractor: TBD
- Tentative Construction Schedule: June 2025 - October 2025
- Project Summary: Removal of existing road pavement and base, adjustments to existing drinking water main, water valves, water services, sewer services, sewer manholes, storm sewer, storm manholes, storm inlets, sewer abandonment, regrading the road, installation and compaction of road base, concrete curb and gutter, concrete sidewalk, sidewalk curb ramps, asphalt pavement, pavement marking, permanent signing, and restoration of the areas outside the roadway.
2026 Pavement Maintenance Projects
↪Construction Updates (Coming Soon)
- Map
- Coming Soon
- Project Types and Limits:
- Crack Sealing
- Various Streets (See 2026 Maintenance Map, Coming Soon) ⇒ TBD (Summer 2026)
- Asphalt Rejuvenation
- Various Streets (See 2026 Maintenance Map, Coming Soon) ⇒ TBD (Summer 2026)
- Asphalt Overlay
- Various Streets (See 2026 Maintenance Map, Coming Soon) ⇒ TBD (Summer 2026)
- 2025 Projects to Finish in 2026:
- Asphalt Pulverize and Overlay
- Shorey Avenue (Camp Phillips Rd (CTH X) to Anastasia Dr) ⇒ American Asphalt of Wisconsin
- Full-Depth Asphalt Mill and Overlay with Concrete Improvements ⇒ RC Pavers, Inc.
- Birch Street (Weston Ave to Cranberry Blvd)
- Asphalt Pulverize and Overlay
- Crack Sealing
2025 Public Works Planning Projects
Projects for 2025 include:
Village of Weston Bicycle and Pedestrian Master Plan, 6999-17-01
- Planning Consultant: HKGi
- Tentative Schedule: Summer 2025 - Summer 2026
- Project Summary: The Village of Weston received a Transportation Alternatives Project (TAP) grant for a Bicycle and Pedestrian Masterplan from the State of Wisconsin which will be incorporated inro the Village’s Comprehensive Plan. The planning study will focus on identifying key gaps in the Village’s bicycle and pedestrian network and looking at projects to close those gaps.
2025 Street and Utility Reconstruction Projects
Projects for 2025 include:
Weston Avenue (CR-X to CR-J)
West Phase-Segment 2 (Von Kanel Street to Ryan Street) - Construction Updates
- Prime Contractor: Integrity Grading & Excavating, Inc.
- Tentative Construction Schedule: 2025 Construction Season
- Project Summary: Removal of existing road pavement and base, installation of drinking water main, water valves, water services, sanitary sewer, manholes, sewer services, storm sewer/culverts, regrading the road, installation and compaction of road base, asphalt pavement, pavement marking, permanent signing, and restoration of the areas outside the roadway. A posted detour route will be in use throughout construction.
Schofield Avenue (Normandy Street to Birch Street) - Construction Updates
- Prime Contractor: Haas Sons, Inc.
- Tentative Construction Schedule: April 2025 - October 2025
- Project Summary: Removal of existing road pavement, removal of curb and gutter, installation of drinking water main, water valves, fire hydrant adjustment, sanitary sewer lining, manhole replacement, sewer service lining, storm sewer inlets, regrading the road, installation and compaction of additional road base, concrete curb and gutter, colored/stamped concrete in the medians, sidewalk curb ramps, section concrete sidewalk replacement, asphalt pavement, pavement marking, permanent signing, signalized pedestrian crossings, traffic signal replacement, and restoration of the areas outside the roadway and within the median.
Fuller Street (Schofield Avenue to Ross Avenue) - Construction Updates
Incl. Storm Sewer Improvements on Rogan Lane (Fuller Street to Heather Street) and at Kellyland Park
- Prime Contractor: Melvin Companies, Inc.
- Tentative Construction Schedule: June 2025 - October 2025
- Project Summary: Removal of existing road pavement and base, installation of drinking water main, water valves, water services, sewer services, storm sewer, storm manholes, storm catch basins, storm inlets, storm water infiltration basin (Kellyland Park), regrading the road, installation and compaction of road base, concrete curb and gutter, concrete sidewalk, sidewalk curb ramps, asphalt multi-use path, asphalt pavement, pavement marking, permanent signing, and restoration of the areas outside the roadway.
Street Maintenance Projects
- Projects Include:
- Crack Sealing
- Various Streets (See 2025 Maintenance Map) ⇒ Precision Sealcoating, Inc. (June-July 2025)
- Asphalt Rejuvenation
- Various Streets (See 2025 Maintenance Map) ⇒ Fahrner Asphalt Sealers, Inc. (June-July 2025)
- Asphalt Overlay
- Various Streets (See 2025 Maintenance Map) ⇒ American Asphalt of Wisconsin (July-August 2025)
- Asphalt Pulverize and Overlay
- Shorey Avenue (Camp Phillips Rd (CTH X) to Anastasia Dr) ⇒ American Asphalt of Wisconsin (July 2025)
- Full-Depth Asphalt Mill and Overlay with Concrete Improvements ⇒ RC Pavers, Inc. (June-October 2025)
- Commerce Drive (Ryan St to Rickyval St)
- Ryan Street (Commerce Dr to Schofield Ave)
- Birch Street (Weston Ave to Cranberry Blvd)
- Cranberry Boulevard (Birch St to Ministry Pkwy)
- Ministry Parkway (Birch St to Cranberry Blvd)
- Franciscan Way (Weston Ave to Ministry Pkwy)
- Weston Avenue (Birch St to Camp Phillips Rd)
- Crack Sealing
- Map: 2025 Street Maintenance Map
2024 Street and Utility Reconstruction Projects
Projects for 2024 include:
Weston Avenue (CR-X to CR-J), West Phase-Segment 1 - Construction Updates
- Project will start the week of September 2nd, following the Labor Day holiday. Project includes reconstruction of the street and construction of new stormwater management facilities to collect and treat stormwater collected along the street corridor before release to nearby natural waterways. The road will be open to local traffic only. A posted detour route will be in use throughout construction.
Jelinek Avenue (Machmueller St to Alderson St) - Construction Updates
- Project will start the week of June 3rd with the contractor getting mobilized to the site and some curb and gutter and sidewalk removals may begin. The road will be open to local traffic, but we do ask the public to utilize the posted detour routes to provide the contractor with sufficient space to complete their work.
- Overall the project consists of replacement of storm sewer inlets and repairs to sidewalk, curb and gutter and curb ramps, various water valve replacements and then repaving of the roadway.
Weston Avenue (Alderson St to Birch St), Alderson St (Weston Ave to Summit Ave), Summit Ave - Construction Updates
- Project is planned to start in mid to late June.
- Overall, the project consists of replacement and installation of new water main through the entire project length, replacement of sanitary sewer on Alderson Street, repaving of all streets with the installation of a roundabout at the Weston Avenue and Alderson Street intersection along with the installation of a multi-use path on Weston Avenue from Alderson Street to Birch Street. This is a joint project between the Village of Weston and Village of Rothschild as portions of the project are in each municipality. Additionally, the Villages are receiving $733,463.03 in State of Wisconsin Grant Funding through the Local Road Improvement Program (LRIP).
East Jelinek Avenue (CR-X to Mesker St) and Von Kanel St (Barbican Ave to Schofield Ave) - Construction Updates
- Project will start in mid June.
- Overall the project consists of replacement and installation of new watermain and sanitary sewer on E. Jelinek Avenue from Camp Phillips Road (CR-X) to Tower Ridge Place, repaving of all streets along with the installation of a multi-use path on E. Jelinek Avenue from Camp Phillips Road (CR-X) to Von Kanel Street and on Von Kanel Street for the entire length of the project. This project also includes the replacement of the water main that connects through the Stillwater Landing Mobile Home Park connecting Schofield Ave water main to the E. Jelinek Avenue water main.
Schofield Avenue and Mesker Street Intersection Improvements - Construction Updates
- Project will start in fall.
- Overall the project consists of installation of new traffic signals at this intersection, intersection lighting, repairs to concrete pavement and curb and gutter, sidewalk and curb ramp improvements, and pavement marking.
Well 4 PFAS Treatment
- Project will start this summer.
- The water utility will be installing a permanent Granular Activated Carbon (GAC) system for PFAS removal for Wells 3 and 4. This project will utilize the existing treatment facility and replace the temporary removal system that is currently being used. The Village received a Safe Drinking Water Loan from the Wisconsin Department of Natural Resources for this project which includes $3.1 Million in Principal Forgiveness for the project.
Weston Business and Technology Park Street Rehabilitation
- Project will start this summer.
- The project includes replacement of concrete curb and gutter and asphalt replacement along the following streets:
- Enterprise Way (Technology to Schofield Avenue / 100' South along Venture Circle)
- Zinser Street (South Termini/STH 29 to Schofield Avenue)
- Commerce Drive (Rickyval Street to Zinser Street)
- Concrete-related work will be completed first as Phase 1 of the project and the asphalt-related work will be completed secondly as Phase 2. The tentative schedule is as follows:
- Phase 1 - Potrykus Construction (Anticipated Schedule: Late June to Later July, weather pending)
- Phase 2 - American Asphalt of Wisconsin (Anticipated Schedule: Late July to Late-September, weather pending)
- If you have questions or concerns, please contact the Public Works Department.
- The project includes replacement of concrete curb and gutter and asphalt replacement along the following streets:
Ross Avenue and Sandy Lane Roundabout Rehabilitation
- Project begins in late summer.
- The project includes replacement of concrete curb and gutter along the center circle and divider medians in the roundabout intersection.
- The anticipated schedule is Early August to Late September, weather pending.
- If you have questions or concerns, please contact the Public Works Department.
Various Asphalt Overlays
- Project begins in late summer. RC Pavers is the Contractor completing the work from late summer through early fall.
- Sandhill Drive
- Siberian Drive
- Sarus Lane
- Brolta Lane
- Country Creek Lane
- Meadow Creak Lane
- Parkway Lane
- Buska Street (South of Shorey Avenue)
- Eau Claire Avenue
- Westfair Street (East of Mesker Street)
- Hilgeman Street
- Chadwick Street (South of Janice Avenue)
- Thomas Avenue (Chadwick Street to Kellyland Street)
2023 Street and Utility Reconstruction Projects
Projects for 2023 include:
Northwestern Avenue
- Improvement of the pavement on Northwestern Avenue from the west village limits to County Road X in cooperation with a federally funded WisDOT program
- To address the deteriorated pavement, the project is proposed to include the following:
- Asphaltic pavement rehabilitation by recycling the existing pavement into aggregate and placing a new asphalt driving surface
- The project will evaluate widening the paved shoulder (from 3-feet to 4-feet) to better accommodate bicycles within the existing roadway width
- No widening of the roadway is planned
- New pavement marking would be installed
- This alternative ensures that the life of the pavement structure and the roadway features are maximized in the most cost-effective manner.
- Asphaltic pavement rehabilitation by recycling the existing pavement into aggregate and placing a new asphalt driving surface
- All work will occur within the existing right of way and no work will occur within the Yellow Banks Park.
- Motorists can expect to encounter daily flagging operations and single-lane closures during construction. Access to adjacent properties will maintained during construction including to the Yellow Banks Park. The contractor will coordinate with property owners throughout construction.
- Please provide any comments or questions on the project by June 15, 2022.
Michael Wodalski
Director of Public Works
Phone: (715) 241-2636
2022 Street and Utility Reconstruction Projects
- Reconstruction of Birch Street south of Weston Ave (Cross Pointe Blvd to Shorey Ave).
- Apache Ln Utility Project. Streets include Trotzer from the west end to Apache Ln and then Apache Ln north to Estate Dr.
2021 Street and Utility Reconstruction Projects
- October 28 Updates:
- October 26 Update:
- Bridge on Ross Ave over the Eau Claire River: Fahrner Asphalt will be on site Tuesday, Oct. 26 thru Wednesday, Oct. 27 (weather dependent) to shot blast the deck patch areas and apply the Epoxy Overlay on the patches. Portable signal lights will be reactivated for this process, and the bridge will be closed to one lane traffic each day during this process. Motorist can expect delays that will be similar as during the past single lane closures.
- Barbican Ave: American Asphalt will be paving the top mat of asphalt (surface) on Barbican Ave., Tuesday, Oct. 26 on the eastbound and westbound lanes. They are projected to finish the areas between the medians on Wednesday, Oct. 27. They will be utilizing flag persons to maintain access to the businesses during this paving project.